A BILL to amend and reenact section four, article three-a, chapter
twenty-two of the code of West Virginia, one thousand nine
hundred thirty-one, as amended, relating to the office of
explosives and blasting and specifying certain certification
and refresher training requirements for blasters to be
proposed in rules.
Be it enacted by the Legislature of West Virginia:

That section four, article three-a, chapter twenty-two of the
code of West Virginia, one thousand nine hundred thirty-one, as
amended, be amended and reenacted to read as follows:
ARTICLE 3A. OFFICE OF EXPLOSIVES AND BLASTING.
§22-3A-4.
Legislative rules on surface-mining blasting;
disciplinary procedures for certified blasters.
(a) The office of explosives and blasting shall propose rules
for legislative approval in accordance with the provisions of
article three, chapter twenty-nine-a of this code, for the purposes
of implementing this article. The rules shall include, but not be
limited to, the following:
(1) A procedure for the review, modification and approval,
prior to the issuance of any permit, of any blasting plan required
to be submitted with any application for a permit to be issued by
the director pursuant to article three of this chapter, which sets
forth procedures for the inspection and monitoring of blasting
operations for compliance with blasting laws and rules, and for the
review and modification of the blasting plan of any operator
against whom an enforcement action is taken by the division of
environmental protection;
(2) Specific minimum requirements for pre-blast surveys, as
set forth in section thirteen-a, article three of this chapter;
(3) A procedure for review of pre-blast surveys required to be
submitted under section thirteen-a, article three of this chapter;
(4) A procedure for the use of seismographs for production
blasting which shall be made part of the blasting log;
(5) A procedure to warn of impending blasting to the owners or occupants adjoining the blasting area;
(6) A procedure to limit the type of explosives and detonating
equipment, the size, the timing and frequency of blasts based upon
the physical conditions of the site so as to: (A) Prevent injury
to persons; (B) prevent damage to public and private property
outside the permit area; (C) prevent adverse impacts on any
underground mine; (D) prevent change in the course, channel or
availability of ground or surface water outside the permit area;
and (E) reduce dust outside the permit area;
(7) Provisions for requiring mining operators to publish the
planned blasting schedule in a newspaper of general circulation in
the locality of the mining operation; and
(8) Provisions for requiring mining operators to provide
adequate advance written notice of the proposed blasting schedule
to local governments, owners and occupants living within the
distances prescribed in subsection (a), section thirteen-a, article
three of this chapter.
(b) The office of explosives and blasting shall propose rules
for legislative approval in accordance with the provisions of
article three, chapter twenty-nine-a of this code. The rules shall
include, but not be limited to, the following:
(1) Provisions for establishing a process for the education,
training, examination and certification of blasters working on
surface-mining operations which require, at a minimum, satisfactory
completion of forty hours of training prior to certification and
completion of a total of eight hours of refresher training for each
year that a blaster's certification is in effect; and
(2) Provisions for establishing disciplinary procedures for
all certified blasters responsible for blasting on surface-mining
operations conducted within this state in violation of any law or
rule promulgated by the division of environmental protection to
regulate blasting.